Location: Map Ta Phut District, Rayong Province
Client Name: Siam Styrene Monomer
End User: Dow Chemical
Project Overview: The project consists of the replacement of the existing timber cooling tower by a new FRP cooling tower under shutdown period. The challenge was to complete the replacement during a limited shutdown period of only 40 days. Hamon-B.Grimm successfully completed the project on time and at customer’s satisfacton.
Product: FRP mechnaical draft Cooling Tower
Our services: Mechanical design / Material supply / Demolish and erection work / Commissioning
Completion Date: March 2020